zevOS

01Case study · New CPO

From installed hardware to paying drivers in six days

Eight connectors, no software team, and a loan repayment schedule that started before the chargers did.

First-time charge point operatorTier-2 city, North IndiaComposite scenario
  • 8

    Connectors at launch

  • 6 days

    Hardware connected to first paid session

  • 0

    Software engineers on the team

The deployment

Profile

Mix
Two 60kW DC units and four AC points
Sites
Three, two of them on partner land
Team
Two founders and one technician

The problem

What was in the way

  1. 01The chargers were installed and idle, because there was no way for a driver to pay.
  2. 02The founders had no basis for setting a price beyond guessing at their electricity cost.
  3. 03Two of the three sites belonged to partners who wanted to know when they would be paid.
  4. 04Nobody would know a charger was down until a driver phoned.

The approach

What was actually done

Each step names the mechanism rather than the outcome, so you can judge whether it would transfer to your situation.

01

QR charging before app building

Per-connector QR codes were printed and fixed at commissioning. A driver scans, sees the connector and the price, pays by UPI and starts — with no install and no account creation before they know what it costs.

02

A defensible opening price

A per-kWh rate was set against landed electricity cost including demand charges, with an idle fee after a grace period to keep DC bays moving. Hour-of-day data from the first weeks then informed the first revision.

03

Partner terms recorded before the first session

Revenue-share terms for both partner sites were entered at commissioning rather than negotiated retrospectively, so the first statement was produced by the system rather than reconstructed.

04

Monitoring from day one

Connectivity and connector state monitoring meant faults surfaced on the dashboard rather than over the phone, and most resets were done remotely by a founder rather than by the technician.

The outcome

What changed

  • First paid session within a week of the chargers connecting.
  • Utilisation per connector visible from the first weekend, which changed where the next two units were placed.
  • Partner statements generated rather than assembled, from the first month.
  • Platform cost stayed proportional to revenue during the slow opening months.

Would the same approach work for you?

Tell us your constraints and we will say honestly which parts of this transfer and which do not.